Skip to content

Florida Construction Lien Law on the Contractor Exam: The Deadlines and Where to Find Them

Updated September 25, 2026 · LicenseReady

Florida's construction lien law is Part I of Chapter 713, Florida Statutes, and on the contractor exam it's mostly a set of deadlines tied to a handful of documents. The owner records a notice of commencement before work starts. A lienor who has no contract with the owner serves a notice to owner within 45 days of starting to furnish. An unpaid lienor records a claim of lien within 90 days of final furnishing and has one year from recording to sue. Each of those numbers sits in a specific section, and the exam rewards the candidate who can find the section in seconds.

Lien questions concentrate on the Business & Finance exam, and the same book that carries the statute is also on the Contract Administration list. This guide lays out the Part I timeline with its section numbers from the 2026 statute text, the owner's side of the paperwork, the payment bond alternative, the traps question writers like, and how to tab the whole thing so a lien question costs you a minute instead of ten.

Where lien law shows up on the exams

The official Business & Finance outline has no area called lien law. Lien material turns up inside several areas: contracts under Managing Administrative Duties, receivables and payables under Conducting Accounting Functions, and Chapter 713 by name under Complying with Government Regulations. That spread is why it feels like it's everywhere on test day. Our practice bank weights it as its own domain because it's one skill, a deadline lookup, wherever the outline files it.

On Contract Administration, the outline is dominated by project contracts and the AIA documents, but the Contractors Manual is on that reference list too, so a lien lookup you rehearsed for Business & Finance works there without changes. The exam math is what makes speed matter: Business & Finance gives you 120 questions in 390 minutes, about 3.25 minutes each, and a lien question you answer from a tab in forty seconds banks time for the accounting problems that need it.

Where Chapter 713 lives in the exam room

Neither 2026 reference list includes Chapter 713 as a standalone book. The Business & Finance list names three items plus three AIA documents: Florida Statutes Chapter 455 (the one statute chapter listed on its own, and the only item the list allows as a bound printed PDF), Builder's Guide to Accounting, and the Contractors Manual. The General, Building and Residential list for Contract Administration and Project Management also includes the Contractors Manual and no separate 713.

So the lien law you'll use on exam day is whatever your edition of the Contractors Manual carries. Our Contractors Manual guide covers what the book reprints; before you tab, open your own copy and confirm it has the Part I sections listed below at their official numbers. You may have seen searches for "section 13 lien law" or a course that points you to a numbered section of a book. Book chapter numbers change between editions, so check your edition and tab by section number, which the statute keeps stable.

The markup rules are the same as for every other reference: underlining in pen or highlighter is allowed, handwritten or typed notes are not, movable tabs like sticky flags are not, and permanent tabs may carry only normal headings. A tab reading "713.08 Claim of lien" is a heading; one reading "90 days after final furnishing" is a note, and notes aren't allowed.

The Part I timeline, section by section

Every deadline below is from the 2026 text of Chapter 713. Learn the order of events cold, and let the book supply the exact number and the exceptions.

  • Notice of commencement, s.713.13: the owner or the owner's authorized agent records it before actually commencing the improvement and posts a certified copy or a notarized statement at the site. If work doesn't start within 90 days of recording, the notice is void (713.13(2)). Unless the notice states otherwise, it stops being effective 1 year after recording (713.13(6)).
  • First inspection, s.713.135(1)(e): when the direct contract is greater than $5,000, a copy of the recorded notice goes to the permitting authority before the first inspection, or later inspections stop. The permit card warning puts it plainly: record and post the notice before the first inspection.
  • Notice to owner, s.713.06(2)(a): every lienor not in privity with the owner, except laborers, serves it before starting or within 45 days after starting to furnish, and in any event before the owner disburses final payment after receiving the contractor's affidavit. Failing to serve it, or serving it late, is a complete defense to enforcement of the lien.
  • Contractor's final payment affidavit, s.713.06(3)(d)1.: when final payment comes due, the contractor gives the owner a sworn affidavit that its lienors who served notice are paid, or lists who isn't. It must be delivered at least 5 days before the contractor sues to enforce its lien.
  • Claim of lien, s.713.08(5): recorded any time during the work or afterward, but not later than 90 days after the lienor's final furnishing. If the original contract is terminated, the deadline is 90 days after termination or 90 days after final furnishing, whichever comes first.
  • Service of the claim, s.713.08(4)(c): a copy goes to the owner before recording or within 15 days after. Missing that makes the lien voidable to the extent the failure prejudiced someone.
  • Duration, s.713.22(1): the lien lasts 1 year after recording (or after recording an amended claim showing a later final furnishing date) unless a suit to enforce it is filed within that year.
  • Notice of contest, s.713.22(2): the owner can serve one, and the lienor then has 60 days from service to sue or the lien is extinguished automatically.

The owner's side of the paperwork

Some questions come from the owner's side and ask what protects the owner. Those answers sit in the same chapter, a few sections over.

  • Small jobs, s.713.02(5): an improvement with a direct contract price of $2,500 or less is exempt from Part I except s.713.05, which covers lienors in privity with the owner.
  • Contract notice, s.713.015: a direct contract greater than $2,500 for work on a one- to four-unit residential property must carry the statutory lien law warning to the owner, in the type size and placement the section specifies.
  • Proper payments, s.713.06(3): an owner who pays according to this subsection, collecting releases and the contractor's final payment affidavit, is protected against paying twice. The owner owes nothing to a lienor, other than a laborer, who hasn't served a notice to owner by the time of a payment.
  • Notice of termination, s.713.132: ends the notice of commencement early. The termination date it states can't be earlier than 30 days after it's recorded, and it has to be served on the lienors the section lists.
  • Waivers, s.713.20: a lien right can't be waived in advance, only for work already furnished. The section supplies the progress-payment and final-payment waiver forms, and a lienor paid by check may condition the waiver on the check clearing.
  • Show-cause order, s.713.21(4): any interested party can ask the circuit court to order the lienor to show cause within 20 days why the lien shouldn't be enforced or cancelled.

Payment bonds: the other set of deadlines

When the contractor furnishes a payment bond under s.713.23, the owner is exempt from the rest of Part I for that direct contract (713.02(6)), and subs and suppliers claim against the bond instead of the property. The bond has its own clock, and it's easy to confuse with the lien clock because two of the numbers match.

  • Notice to the contractor: a lienor not in privity with the contractor, other than a laborer, serves written notice, before or within 45 days after beginning to furnish, that it will look to the bond. A timely notice to owner served on the contractor satisfies this.
  • Notice of nonpayment: served under oath on the contractor, with a copy to the surety, no later than 90 days after the lienor's final furnishing.
  • Suit on the bond: within 1 year, measured the way 713.23(1)(e) spells out. Read that paragraph once with a highlighter in hand; the measuring point is where bond questions get tricky.

How lien questions are built, with original examples

Most lien questions test whether you started the right clock, picked the right party, or remembered an exception. The examples below are ours, written to show the pattern; none is an exam question.

Which clock. A tile supplier first delivers to a house on March 3 and makes its last delivery on June 20. The notice to owner runs from the first delivery and the claim of lien from the last one. Candidates who run both from the same date lose the point.

Final furnishing. A drywall sub finishes on August 1, gets called back on September 10 to patch its own dings, and wants to count 90 days from the callback. Section 713.01 defines final furnishing as the last date the lienor furnishes labor, services, or materials, and excludes correcting deficiencies in work already performed. The certificate of occupancy doesn't move the date either.

Who must serve. A laborer and a material supplier to a subcontractor are both unpaid on the same job. The supplier needed a notice to owner; the laborer is exempt. Privity decides the answer, and the definitions in 713.01 settle who counts as what.

Weekend math. Under s.713.011, when the last day of a Part I time period lands on a Saturday, Sunday, or listed holiday, the period runs to the end of the next business day.

How to tab and drill Chapter 713

Tab the handful of sections that answer most questions, in statute order: 713.01 (definitions), 713.06 (notice to owner and proper payments), 713.08 (claim of lien), 713.13 (notice of commencement), 713.20 (waivers), 713.22 (duration and notice of contest), and 713.23 (payment bond). Highlight the deadline sentence inside each one so your eye lands on it after the flip.

Then drill the lookups rather than rereading the chapter. Answer lien questions against the clock, look up every miss in your own tabbed book, and track whether your time per lookup is falling. Once you can get from question to highlighted sentence in under a minute, move that study time to the accounting problems. If you're not sure where you stand on Business & Finance overall, the free readiness quiz takes a few minutes and shows which outline areas need the work.

Highlight the question, underline the answer

Don't just tab your books — mark them as you practice. Every time a question sends you into a reference, leave a two-part mark behind: highlight the passage the question is about, and underline the exact words that answer it. Do this through your whole question bank and the book turns into a map of the tested material — so on exam day you recognize the spot, not just the section.

  1. 1

    Highlight what the question asks about

    When you look up a practice question, highlight the sentence or table the question turns on. That block is now a visual landmark you'll spot on a fast flip.

  2. 2

    Underline the exact answer

    Inside the highlight, underline the specific number, deadline, or phrase that is the answer — with a fine-tip pen. Highlight = the topic; underline = the fact.

  3. 3

    Color-code by what trips you up

    Use one highlighter color for deadlines and numbers, another for definitions, a third for the answers you got wrong twice. Your weak spots become the brightest marks in the book.

  4. 4

    Let your tabs and marks compound

    A tab gets you to the chapter; the highlight gets you to the paragraph; the underline gets you to the answer. Built up across a full question bank, that three-layer trail is the open-book skill the exam actually tests.

The reference lists allow underlining with pen or highlighter, bar handwritten and typewritten notes in the books, and bar making any marks during the exam — so every mark goes in before you walk in, and none of them can be written notes.

Gear for marking your books

The cheap supplies that make an open-book exam fast: permanent tabs, highlighters, and pens for the marking method above, plus the tools a few trade exams require.

Bring this

Permanent self-adhesive index tabs

Write-on tabs that stick for good. The reference lists ban movable Post-it flags, and the candidate booklet permits only permanently attached tabs with normal chapter or page headings; a tab that peels off without damaging the page counts as removable. Buy tabs meant to stay put and write headings only.

Your tab set is the single highest-leverage thing you bring. One tab per spot in our guides means a cited section is a flip away, not a scavenger hunt.

Shop on Amazon
Bring this

Assorted-color highlighters

A multi-color pack. The reference lists expressly allow underlining with highlighter, and a color code (one color per topic, or question-vs-answer) makes the right line jump off the page.

Color-coding is how you find an answer in two seconds instead of twenty. Pair these with the marking method below.

Shop on Amazon
Bring this

Fine-tip pens for underlining

Smooth, fine-point pens. Pen underlining is allowed and is cleaner than a highlighter for marking the exact answer phrase inside a highlighted block.

Highlight the topic, underline the answer. A fine tip keeps a long statute sentence readable instead of buried under ink.

Shop on Amazon

Architect's scale (1/4" and 1/8")

Required for the trade-knowledge exams — the reference lists tell every candidate to bring one.

Plan-reading questions are unanswerable without it. Practice reading at 1/4" and 1/8" before exam day so the tool isn't new under the clock.

Shop on Amazon

Silent, battery-operated calculator

The candidate booklet permits calculators that are silent, hand-held, battery-operated, nonprinting, and without an alphabetic keypad, and says solar models are not recommended. Fresh batteries.

Job-costing, ratios, and takeoff math are timed. Use a calculator you already know — exam day is the wrong time to learn one.

Shop on Amazon

As an Amazon Associate, LicenseReady may earn a commission from qualifying purchases made through these links — at no additional cost to you. We only list gear we'd bring to the exam ourselves.

The study-notes series, by email

Three short emails over ten days: the study habits with real research behind them, the retake-fee math, and how to know you're actually ready. Then we leave you alone — occasional product updates only, unsubscribe anytime. See the Privacy Policy.

Go deeper: the exams behind this guide

Each exam has its own breakdown: format, weighted domains, sample questions, and the reference books it draws from.

Frequently asked questions

What are the Florida lien law deadlines for the contractor exam?

Under the 2026 text of Chapter 713, the main ones are: notice to owner within 45 days of starting to furnish (s.713.06), claim of lien recorded within 90 days of final furnishing (s.713.08), a copy served on the owner within 15 days of recording, and suit to enforce within 1 year of recording (s.713.22). A notice of contest from the owner cuts the suit window to 60 days from service. The contractor's final payment affidavit must reach the owner at least 5 days before the contractor sues.

Is Florida Statutes Chapter 713 allowed in the Business and Finance exam?

Not as a separate book. The 2026 Business & Finance reference list names Chapter 455, Builder's Guide to Accounting, the Contractors Manual, and three AIA documents; Chapter 713 isn't listed on its own. The lien law you use in the room is what your edition of the Contractors Manual contains, so check your edition before exam day.

Who has to serve a notice to owner in Florida?

Every lienor who isn't in privity with the owner, except laborers, under s.713.06(2)(a). That covers subcontractors, sub-subcontractors, and material suppliers who contracted with someone other than the owner. A contractor with a direct contract with the owner doesn't serve one.

Does the notice to owner deadline run from first or last furnishing?

From the start. Section 713.06(2)(a) requires service before commencing or within 45 days after commencing to furnish labor, services, or materials, and in any case before the owner's final payment after the contractor's affidavit. The 90-day claim of lien deadline is the one that runs from final furnishing.

What is a notice of commencement and when does it expire?

It's the document the owner records under s.713.13 before starting an improvement, identifying the property, owner, contractor, surety, and lender. It's void if work doesn't begin within 90 days of recording, and unless it states a different date, it stops being effective 1 year after recording. When the direct contract is greater than $5,000, a copy must be filed with the permitting authority before the first inspection.

Is lien law a big part of the Florida Business and Finance exam?

It shows up in several outline areas rather than one, including contracts, receivables and payables, and Florida law, so you'll see it throughout the exam. The questions are mostly deadline and document lookups, which makes them some of the most recoverable points on the test if your Contractors Manual is tabbed and you've rehearsed the flips.

Keep reading

LicenseReady is an independent exam-preparation service. We are not affiliated with, endorsed by, or approved by the Florida Department of Business and Professional Regulation (DBPR), the Construction Industry Licensing Board (CILB), or Professional Testing, Inc. All practice questions are original content created by LicenseReady — they are not actual examination questions. Exam-structure information comes from publicly available DBPR publications. Third-party product names (AIA, ACCA, and others) are trademarks of their respective owners, used only to identify the referenced works.

Privacy Policy · Terms of Service