Shell, Deck & Finishes

30% of this exam

How a pool gets built and why it stays in the ground: steel and shotcrete/gunite shells (and vinyl-liner and fiberglass pools), the bond beam, decks and coping, tile and trim, accessories, interior finishes and the start-up that follows — plus the forces (settlement and groundwater) that crack or float pools when the details are skipped. The largest domain on the construction exams; questions test the sequence, the detail, and the reason behind it.

What the exam asks

  • Build sequence: what comes before what, from excavation through plaster and fill.
  • Why details exist: soil support, groundwater uplift, joints, rebound, wet cure and fill rules.
  • Shotcrete and steel: bar size numbers, chairs and dobies, shell thickness, 4,000 psi at 28 days.
  • Code numbers for barriers, steps and depth markers, plus the start-up that protects new plaster.
  • Pool volume in gallons and shotcrete yardage with a waste allowance.

Part 1 of 5

Build order, soil and groundwater

A pool is built in a fixed order, and most of the order exists because of what the ground does. Soil that settles and water that pushes up are behind many of the exam's why questions.

The sequence is the story

Excavate to grade from a benchmark elevation → set plumbing rough-in and tie the steel grid → shoot the shell (gunite = dry mix with water added at the nozzle; wet-mix shotcrete arrives mixed) → tile and coping → deck → plaster last, then fill. Questions love to ask what comes before what.

The shell is only as good as the soil

Overdig cannot be fixed by pushing loose soil back — uncompacted fill settles and leaves the shell unsupported. Correct it with compacted fill, lean concrete, or a thickened section. On wet sites, dewater with sump or well points so steel and concrete go in dry.

Water pushes both ways

A full pool pushes out; a high water table pushes up. A hydrostatic relief valve in the main drain sump lets groundwater into an empty shell so the pool doesn't float. Never drain a pool in wet ground without thinking about uplift.

In your books: Construction-method questions such as dewatering and water stops come from the handbook side. Shell, deck and elevation requirements are lookups in the FBC pool provisions.

Part 2 of 5

Steel and shotcrete

The shell is a steel grid inside shotcrete. Know the bar numbers, how the steel is held in place, and how the shotcrete is placed, tested and cured. Strength is proven with test panels and cores, not assumed.

Steel is a schedule, and bar numbers are eighths

Bar size number = diameter in eighths of an inch (#3 = 3/8 in, #4 = 1/2 in, #5 = 5/8 in). Shells are typically #3 bars on a 12-inch grid in floors and walls with extra bars at the bond beam, steps and corners; the engineer's drawing governs. Bars sit on chairs or dobies so they end up centered in the shell with cover on both faces, laps are made where the drawings say, and ties hold the mat still during shooting. Placing Reinforcing Bars is the approved-list reference.

Work it: Bar size number

Diameter in inches = Bar number ÷ 8

Bar diameter

5 ÷ 8 equals 0.625 in.

Shotcrete quality is proven, not assumed

Bars are placed so shotcrete can be shot through and around them (closely spaced or bundled bars leave shadows); #3 = 3/8 in., #4 = 1/2 in. — the number is eighths of an inch. Construction joints are tapered, cleaned of rebound and dampened; rebound is never reused. Strength is proven with test panels shot during placement and cores tested at the specified age.

Shotcrete: thickness, strength and cure

A typical residential shell is about 6 inches in the floor and walls, thickening to an 8-inch wall at the bond beam, with the beam itself 12 inches deep; the specification calls for 4,000 psi at 28 days in most Florida work. Rebound (material that bounces off) is waste — it is never shoveled back into the shell. The shell is kept wet for about seven days of curing so the surface does not dry-shrink and craze, and the plumbing and steel are inspected before any shotcrete goes in.

Work it: Shotcrete yardage

Cubic feet = Surface area × Thickness in feet (inches ÷ 12). Cubic yards = Cubic feet ÷ 27. Order = Cubic yards × (1 + Waste allowance).

SF
in.
%

Cubic feet in place

1,400 SF × 6 in. ÷ 12 equals 700 cu ft

Cubic yards in place

cubic feet ÷ 27 equals 25.9 cy

Cubic yards to order (a thicker beam and steps add to the surface figure)

cubic yards × (1 + 15%) equals 29.8 cy

In your books: Shotcrete placement questions (wet or dry mix, rebound, curing) answer from the ACI Guide to Shotcrete. Rebar support and clearance come from Placing Reinforcing Bars. Both are on the approved list.

Part 3 of 5

Vinyl-liner and fiberglass pools

Not every pool is a shotcrete shell. These two types fail in different ways, so they are built and backfilled differently.

Vinyl-liner and fiberglass pools fail in different ways

A vinyl pool is a panel wall (steel, aluminum or polymer) braced and backfilled, a troweled vermiculite or sand floor, and a liner fitted warm so it stretches into the corners without wrinkles; sharp stones and ground water under the floor are the enemy. A fiberglass shell is set on a compacted sand or gravel bed, leveled, then backfilled with pea gravel or flowable material in lifts while water is added in step so the pressures stay equal — a fiberglass shell is never left empty or backfilled dry against a dry shell.

Part 4 of 5

Tile, coping, deck and joints

The bond beam, tile, coping and deck carry the water and the movement. The beam is set level because the tile, skimmer, coping and depths hang off it, and the deck is jointed so it cannot push on the shell.

Tile, coping and deck details carry the water

The bond beam is set level from the benchmark because the waterline tile, skimmer throat, coping and depths all hang off it. Waterline tile goes in latex-modified thin-set and immersion-rated grout. Precast coping sits in a mortar bed with corners mitered; decks slope about 1/4 in. per foot away from the pool and are separated from the coping by an expansion joint so soil movement does not push on the shell.

Joints: expansion, control and bond

A deck needs an expansion joint (compressible filler with a flexible mastic cap) between the deck and the coping or the pool wall, so the deck can move without levering the shell. Control joints cut the deck into panels so shrinkage cracks happen where you put them. Where new deck meets old, the old edge is cleaned and a bonding agent or dowels tie the pour so it does not separate at the seam. Coping is set on a mortar bed with an overhang, and the waterline tile is bedded below it before the plaster.

Joints and cracks have meanings

An expansion joint isolates deck movement from the beam and coping. A water stop embedded across a cold joint blocks seepage where two placements meet. Structural cracks go through the shell (settlement, soil movement) and can leak; check cracks (crazing) are shallow plaster shrinkage and cosmetic.

In your books: If a question describes a crack or failure, ask what moved. Soil under the shell is structural. Plaster shrinkage is cosmetic crazing.

Part 5 of 5

Accessories, plaster and start-up

The last part is the code numbers for barriers, steps and markers, and the clock that starts when the plaster goes on. Start-up chemistry decides how the finish looks a month later.

Accessories and finishes have code numbers

Residential barriers (FBC-B §454.2.17): 48 in. high, 20 in. from the water's edge, 2 in. bottom clearance (4 in. over a deck), no 4-in. sphere, pickets 1¾ in. apart. Diving equipment only where the pool meets the ANSI/APSP/ICC-5 envelope for that board. Public pool steps: treads at least 10 in., risers no more than 12 in.; depth markers 4 in. high at slope changes and intervals. Plaster is brushed from start-up to remove plaster dust before it hardens.

Plaster and finishes have a clock

White plaster (marcite), quartz and pebble finishes go on about 1/2 inch thick over the cured, acid-etched or bond-coated shell. The pool is filled immediately and continuously — never stopped partway (a ring) — and the finish is brushed daily, run without heat, and balanced carefully for the first weeks because fresh plaster drives pH up and sheds dust. Crazing, mottling and etching in the first month trace back to the start-up chemistry, not the plasterer.

Work it: Pool volume in gallons

Average depth = (Shallow + Deep) ÷ 2. Cubic feet = Length × Width × Average depth. Gallons = Cubic feet × 7.48.

ft
ft
ft
ft

Average depth

(3 ft + 8 ft) ÷ 2 equals 5.5 ft

Volume

32 ft × 16 ft × average depth equals 2,816 cu ft

Gallons (kidney and free-form pools use the handbook's shape factors)

cubic feet × 7.48 equals 21,064 gal

In your books: Barrier, step, gutter and depth-marker numbers are section 454 lookups in FBC Building. The pool lists do not include FBC Residential. Volumes, start-up and plaster care are the handbook.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Gunite vs wet-mix shotcrete
Gunite: dry mix in the hose, water at the nozzle; wet-mix: fully mixed before pumping
Steel placement
Tied as a grid after excavation/plumbing, before the shell is shot
Hydrostatic relief valve
In the main drain sump; admits groundwater to keep an empty shell from floating
Overdig
Fill with compacted material or lean concrete — never loose soil
Waterline tile
Cleanable glazed band where oils and scale collect; plaster would stain and etch
Coping types
Cantilevered = deck poured over the beam edge; precast = separate units set in mortar
Bar sizes
#3 = 3/8 in., #4 = 1/2 in. (number ÷ 8 = inches)
Deck slope
About 1/4 in. per ft (1/8 in. minimum) away from the pool, typically 4 in. thick
Mortar types
Type S or M for below-grade and high-load masonry; N for general above-grade work
Shotcrete strength
4,000 psi at 28 days is the usual Florida spec; proven by cores or test panels, not assumed.
Typical shell thickness
≈ 6 in floor and walls, 8 in at the bond beam, beam 12 in deep — the engineer's drawing governs.
Rebound
Never worked back into the shell; it is waste.
Bar size number
Eighths of an inch: #3 = 3/8 in, #4 = 1/2 in, #5 = 5/8 in.
Chairs and dobies
Hold the steel off the soil and centered in the shell so it has cover on both faces.
Wet cure
Keep the shell wet about 7 days; dry shrinkage crazes the surface.
Vinyl liner fit
Install warm so it stretches smooth; smooth floor, no stones, no ground water under it.
Fiberglass backfill
Backfill in lifts while filling with water so the pressures match; never leave the shell empty.
Plaster fill rule
Fill immediately and without stopping; brush daily; no heat; balance the water for the first weeks.
Expansion vs control joints
Expansion joint (filler + mastic) between deck and coping; control joints cut the deck into panels.

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

96 questions in this domain, each with an explanation and source.