Bidding & Procurement

12% of this exam

How projects get from documents to a signed contract: bid bonds, addenda, alternates and allowances, and the public-bidding rules. Questions test document vocabulary and the rules that keep competitive bidding fair — including what happens when a bidder makes a mistake.

What the exam asks

  • Bidding vocabulary: addenda, alternates, allowances, bid security and which form covers what.
  • What changes the documents (written addenda only) and what does not (verbal answers).
  • Responsive versus responsible, and which defects make a low bid unacceptable.
  • Bid bond recovery, clerical bid mistakes and the contract sum after an accepted alternate.

Part 1 of 5

The bidding documents and what changes them

Every bidder prices the same set of documents. This part covers how those documents get changed before bid opening, and what a bidder is held to whether it reads the site or not.

Addenda change the documents before bids open

An addendum is a written modification to the bidding documents issued before bid opening. It binds every bidder and must be acknowledged in the bid — missing an acknowledgment can make a bid non-responsive.

Only a written addendum changes the documents

Answers given out loud at the pre-bid conference do not modify the bidding documents. Interpretations, corrections, and changes are made by written addendum sent to all plan holders. A big change on the eve of the opening is handled by issuing the addendum and postponing the opening (also by addendum), so every bidder has time to get revised sub quotes.

Substitutions and unit prices before the bid

A substitution request goes in writing by the stated deadline before bid opening, with enough data for the architect to judge equivalence. If approved it is issued by addendum so every bidder can price it. Verbal approvals do not count. Unit prices on a lump sum bid form pre-price the work most likely to change in quantity, typically earthwork, so a later change is arithmetic instead of a negotiation.

The site visit binds you whether you go or not

Site examination clauses charge every bidder with what a reasonable visual inspection would show: access limits, adjacent structures, visible utilities, surface conditions. A contractor cannot collect extras for an obvious condition it could have seen.

In your books: Addenda, and the rule that only a written addendum changes the documents, are in AIA A701 Instructions to Bidders. Tab it.

Part 2 of 5

Alternates and allowances

Owners flex scope and price two ways. An alternate is a priced option decided at award. An allowance is a placeholder settled later. Know which is which.

Alternates and allowances flex the scope and price

An alternate is a separately priced add or deduct to the base bid that the owner may accept at award. An allowance is a placeholder sum in the contract for items not yet selected (A201 §3.8); when the real cost is known, a change order adjusts the difference.

Work it: Contract sum with alternates

Contract sum = Base bid + Accepted add alternates − Accepted deduct alternates

$
$
$

Contract sum

$3,200,000 + $145,000 − $0 equals $3,345,000

In your books: Alternates are covered in AIA A701 Instructions to Bidders. Allowances are in AIA A201 §3.8.

Part 3 of 5

Bid security and the bid bond

The bid bond backs the promise to sign the contract. The recovery math turns on one rule: the owner gets the difference to the next bid, capped at the penal sum.

The bid bond backs the promise to sign

A bid bond (AIA A310, commonly 5–10% of the bid) guarantees that the winning bidder will enter into the contract and furnish the required performance and payment bonds. Recovery is typically limited to the difference between the low bid and the next bid, capped at the bond's penal sum.

How much a bid bond actually pays

The surety owes the difference between the defaulting bid and the next acceptable bid, never more than the penal sum. With a 5% bond on a $1,850,000 bid the penal sum is $92,500; if the next bid is $1,912,000 the difference is $62,000, and that is what the owner recovers. Bid security can also be a certified or cashier's check.

Work it: Bid bond recovery

Penal sum = Bond % × Bid. Recovery = Next bid − Defaulting bid, never more than the penal sum.

%
$
$

Penal sum (the ceiling)

5% × $1,850,000 equals $92,500

Difference to the next bid

$1,912,000 − $1,850,000 equals $62,000

Owner recovers (the smaller of the two)

Lesser of difference and penal sum equals $62,000

In your books: Bid security is covered in AIA A701 Instructions to Bidders. The bid bond form is AIA A310.

Part 4 of 5

Public awards: responsive, responsible and bid mistakes

Public work goes to the lowest bidder who passes two separate tests. The usual mistakes are mixing the two tests up and treating every defect as fatal.

Public awards and bid mistakes

Public contracts go to the lowest responsive AND responsible bidder — a low bid can be rejected for either failing. A bidder who promptly proves a genuine clerical mistake (not an error in judgment) may usually withdraw without forfeiting bid security, but may never revise the bid upward after opening.

Responsive is about the bid; responsible is about the bidder

A responsive bid conforms in all material respects to the bidding documents. A responsible bidder has the capability, integrity, and financial and bonding capacity to do the work. They are separate tests, and a public award needs both. If the low bid fails either one, the authority moves to the next lowest bid and runs the same two tests on it.

Which defects kill a bid

The question is whether the defect could give the bidder an unfair advantage or leave the bid's scope unclear. Failing to acknowledge an addendum that changes price or scope is material: the bid may not include the changed work. Failing to acknowledge an addendum that only fixes an administrative detail carries no such risk and is usually a waivable informality.

In your books: Public bidding rules are statutory. The Contractor's Manual chapters on public construction bidding cover responsive and responsible bidders and the bid-mistake doctrine.

Part 5 of 5

Subcontractor quotes, protests and form numbers

Bid day is also when sub prices move around. This part covers the fair and unfair ways to handle them, what a losing bidder can do, and the form numbers to know.

Bid shopping, bid peddling, and leveling

Bid shopping is the GC disclosing a sub's price to its competitors to drive the number down. Bid peddling is the sub's version: after award, offering to undercut the price the GC carried. Both are condemned by industry ethics codes. Bid leveling is the legitimate work of comparing quotes on equal scope.

Protests, flow-down, and the form numbers

An aggrieved bidder on public work files a bid protest with the awarding authority, and the deadlines are short; wait and the right is waived. A lien is not available because public property cannot be liened. A flow-down clause passes the prime contract's requirements (scope, schedule, insurance, claims procedure, notice periods) through to the subcontractor. Know the forms: A701 Instructions to Bidders, A310 bid bond, A401 subcontract, A201 general conditions.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Bid bond amount
Commonly 5–10% of the bid (AIA A310)
Addenda
Issued before bid opening; must be acknowledged in the bid
Public award standard
Lowest responsive and responsible bidder
Clerical bid mistake
Prompt, documented mistake → withdraw without forfeiting bid security; no upward correction
Alternate vs allowance
Alternate = priced scope option at award; allowance = placeholder sum adjusted later (A201 §3.8)
Responsive
The bid conforms to the bidding documents in all material respects
Responsible
The bidder has the capability, integrity, and financial and bonding capacity
Low bid rejected
Move to the next lowest bid and test it the same way — FS 255.20
Bid bond recovery
Lesser of (next bid − defaulting bid) and the penal sum
Bid security forms
Bid bond from a surety, or a certified or cashier's check
Pre-bid conference
Oral statements do not change the documents; only written addenda do
Substitution before bid
Written request by the deadline; approval issued by addendum to all bidders
Bid shopping vs peddling
Shopping = GC discloses a sub's price; peddling = sub offers to undercut after award
Accepted alternate
Added to (or deducted from) the base bid to set the contract sum
Bid protest
Filed with the awarding authority on short deadlines; public property cannot be liened
Flow-down clause
Binds the sub to the GC as the GC is bound to the owner — AIA A401
AIA A701
Instructions to Bidders: addenda, alternates, bid security, withdrawal

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

26 questions in this domain, each with an explanation and source.