Bonds & Insurance

8% of this exam

Who is protected by which bond or policy, and what the surety does when a contractor defaults. The core skill is matching: performance bond → owner gets completion; payment bond → subs and suppliers get paid; builder's risk → the work itself; general liability → third parties.

What the exam asks

  • Matching: performance bond to the owner, payment bond to subs and suppliers, builder's risk to the work, general liability to third parties.
  • Who is principal, surety and obligee, on a prime bond and on a subcontractor's bond.
  • What the surety may do after a proper default, and why the penal sum is its ceiling.
  • Insurance details: additional insured, waiver of subrogation, wrap-ups, professional liability and certificates.

Part 1 of 5

Who each bond protects

Most questions here are matching questions. Know the three bonds, the three parties on a bond, and why public work leans on bonds instead of liens.

The three bonds protect different people

A bid bond guarantees the bidder will sign and bond the job. A performance bond guarantees the owner that the work will be completed per the contract. A payment bond guarantees subcontractors, laborers, and suppliers will be paid — on bonded private projects they claim against the bond instead of liening (FS 713.23), and on public projects, where property cannot be liened, against the bond FS 255.05 requires.

Who is who on a bond

The principal is the party whose performance is guaranteed. The surety guarantees it. The obligee is the party protected. On a prime contract that is contractor, surety, owner. On a subcontractor's bond the sub is the principal and the GC is the obligee. A dual obligee rider adds the lender as an obligee with essentially the owner's rights and obligations, including paying the contract balance.

Public work is bonded because it cannot be liened

Public property is not subject to construction liens. Section 255.05 fills the gap by requiring the contractor on a public building to furnish a bond before starting: the payment bond is the fund subs and suppliers claim against, and claimants must follow the statute's notice and suit requirements. On private work, section 713.23 exempts the owner's property from liens when a qualifying payment bond is in place and sends unpaid subs and suppliers to the bond.

In your books: Payment-bond-instead-of-lien questions point to FS 713.23. The bond exempts the property and routes claimants to the surety.

Part 2 of 5

A bond is credit, not insurance

The surety expects to be repaid, and that one idea explains the indemnity agreement, the premium and the penal sum.

A bond is not insurance

A bond is a three-party guarantee: principal (contractor), obligee (owner), surety. The penal sum — commonly 100% of the contract price — is the cap on the surety's liability, and the surety expects the contractor to repay whatever it pays out.

Suretyship is credit, not loss-sharing

Insurance spreads expected losses across many insureds. A surety underwrites expecting no loss at all: it prequalifies the contractor's capital, capacity, and character, and it takes a general indemnity agreement from the contractor, and often from its owners personally, to be repaid for anything it pays out. The penal sum is still the ceiling: on a $4,000,000 bond the surety owes no more than $4,000,000 even if completion costs more.

Work it: Penal sum as the ceiling

Penal sum = Bond percentage × Contract price. The surety owes no more than the penal sum.

$
% of price
$

Completion cost above the penal sum

$2,750,000 − penal sum equals $250,000

Penal sum, the most the surety owes under the bond

100% of price% × $2,500,000 equals $2,500,000

Bond premiums are a cost of the work

The contractor buys the bonds as principal and pays the premium, figured on the contract amount from the surety's rate schedule. The premium is carried in the bid, so the owner pays for the bonds it requires. Waive the bond requirement and the price drops by that line.

Part 3 of 5

When the contractor defaults

The surety has four ways to respond, but only if the owner has followed the bond's steps first.

Surety options after default

When the owner properly declares default, the performance bond surety may: take over and complete the work itself (takeover), tender a replacement contractor to the owner, finance the original contractor to finish, or pay the owner the cost to complete up to the penal sum.

The owner has to follow the bond's steps

A performance bond conditions the surety's obligation on the bond's procedure: notice, a formal declaration of default, termination of the contract, and a chance for the surety to pick its completion option. An owner that replaces the contractor on its own strips the surety of that choice and can discharge the surety in whole or in part.

In your books: Bond mechanics (penal sum, surety options, claim procedure) are in the A312 forms.

Part 4 of 5

Insurance matches the loss

Each policy answers one kind of loss. Pick the policy by asking what was hurt: the work, a third party, or an employee.

Insurance matches the loss

Builder's risk: physical loss to the work under construction (fire, wind, vandalism). CGL: third-party bodily injury and property damage. Workers' comp: employee injuries. Additional insured status puts a sub's insurer behind the GC and owner for liability arising from the sub's work; a waiver of subrogation stops the property insurer from suing project participants for losses it covered.

Property insurance and indemnity under A201

A201's default puts the duty to buy property insurance for the full insurable value of the work on the owner, on an all-risk or equivalent basis. Builder's risk answers for the work and for materials intended for it, including materials stored on site; a delivery driver hurt on site is a liability claim, not a builder's risk claim. An indemnification clause moves responsibility for third-party claims by contract, and it works together with the insurance requirements that fund it.

In your books: Insurance requirements and the subrogation waiver are A201 Article 11.

Part 5 of 5

Wrap-ups, design work and certificates

Three places where the paperwork and the coverage can part ways: who sponsors the program, what CGL leaves out, and what a certificate really proves.

Wrap-ups, professional liability, and certificates

In a wrap-up (OCIP when the owner sponsors it, CCIP when the contractor does) the sponsor buys project coverage for all enrolled contractors, and they deduct their own insurance cost from their bids. It covers on-site operations only; a sub's fabrication shop stays on the sub's policies. CGL policies exclude professional services, so a design-builder needs professional liability coverage for design. A certificate of insurance is information only: it confers no rights and does not change the policy. The protection comes from the endorsement.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Performance bond
Guarantees completion per contract terms — protects the owner (AIA A312)
Payment bond
Guarantees payment to subs and suppliers (AIA A312; FS 713.23 exempts bonded property from liens)
Penal sum
The surety's maximum liability, typically 100% of contract price
Surety default options
Takeover, tender a new contractor, finance the principal, or pay the cost to complete
Builder's risk
Property insurance on the work itself during construction
Waiver of subrogation
Insurer cannot pursue project parties for losses the property policy covered (A201 Art. 11)
Bond parties
Principal (performs), surety (guarantees), obligee (protected)
Subcontractor bond
Sub is the principal; the GC is the obligee — AIA A401
Dual obligee rider
Adds the lender as an obligee on the performance bond
General indemnity agreement
Contractor (and often its owners personally) repays the surety
Declaration of default
Owner follows the bond's notice and termination steps or risks discharging the surety
Bond premium
Paid by the contractor, carried in the bid, based on the contract amount
Public projects
No lien rights; payment and performance bond required — FS 255.05
OCIP / CCIP
Owner- or contractor-sponsored wrap-up; on-site operations only
Professional liability
Design services are excluded from CGL; design-builders need it
Certificate of insurance
Informational only; confers no rights and does not amend coverage
Property insurance default
Owner buys it, all-risk, full insurable value — A201 Art. 11
Additional insured
Extends the sub's policy to the GC and owner for the sub's operations

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.

Reading isn't learning. Retrieval is.

27 questions in this domain, each with an explanation and source.