Payments, Documentation & Closeout
10% of this examThe paper that runs the project: submittals, the schedule of values, pay applications and retainage, then the closeout sequence — substantial completion, punch list, consent of surety, and record drawings. Expect at least one retainage math question; the rest are definitions straight out of A201 Articles 3, 9, and 12.
What the exam asks
- Retainage math: payment due is work completed to date times (1 − retainage), less previous payments.
- Who does what in submittals, RFIs and the substantial completion sequence under A201.
- What substantial completion starts: the correction period, utilities and insurance responsibility, and the end of delay damages.
- What final payment needs, including consent of surety, and what accepting it waives.
Part 1 of 5
Submittals and RFIs
Shop drawings, product data and samples go through the contractor first, then the architect. The review has a narrow purpose, and the contractor keeps the responsibility for the field.
Submittals prove conformance, not transfer design
Shop drawings, product data, and samples (A201 §3.12) show how the contractor will conform to the design concept. The architect's review is for design-concept conformance only — it does not shift design responsibility or relieve the contractor of dimensions, quantities, or means and methods.
The submittal chain and the RFI
The GC reviews and approves shop drawings first, checking field dimensions, coordination between trades, and means of construction; its stamp says that check was done. The architect then reviews for conformance with the design concept only. An RFI is a clarification tool. An RFI answer does not by itself change the contract sum or time; if the answer adds scope, flag it and run it through the change process.
In your books: A201 §3.12 covers submittals. Tab it with §3.11, the record documents section.
Part 2 of 5
Pay applications and retainage
Every payment is measured against the schedule of values. The retainage math is the most likely calculation in this domain, so write the formula before you touch the numbers.
Payment runs through the schedule of values
Before the first pay application, the contractor submits a schedule of values allocating the contract sum among work items (A201 §9.2); each application (G702/G703) measures progress against those lines. Retainage — typically 5–10% — is withheld from each progress payment as security. Payment due = (work completed × (1 − retainage)) − previous payments.
Retainage is figured on the total earned to date
Payment due = (work completed to date × (1 − retainage)) − previous payments. $600,000 complete at 10% retainage with $450,000 already paid: $540,000 − $450,000 = $90,000. Do not apply retainage to this month's work alone. Some contracts stop withholding at 50% complete: on a $2,000,000 job at 10% to the halfway point, $100,000 is held on the first $1,000,000 and nothing on work after that.
Payment due = (Work completed to date × (1 − Retainage)) − Previous payments
Earned to date, less retainage
$600,000 × (1 − 10%%) equals $540,000
Payment due
Earned less retainage − $450,000 equals $90,000
Retainage held = Contract sum × Stop point × Retainage rate. Nothing is withheld on work after the stop point.
Work that carries retainage
$2,000,000 × 50% complete% equals $1,000,000
Most retainage ever held
Work that carries retainage × 10%% equals $100,000
A front-loaded schedule of values is a problem
The schedule of values goes in before the first pay application and should show the real value of each item. Loading the early lines pays the contractor more than it has earned. If the contractor later defaults, the money left in the contract is not enough to finish, which is why architects and sureties watch for it.
Stored materials can be billed
The G702/G703 form has a column for materials presently stored. Material suitably stored on site is billable before it is installed, normally backed by invoices or bills of sale and protected against loss with secure storage and insurance.
Why an architect may withhold certification
A201 allows withholding to the extent needed to protect the owner: defective work not remedied, third-party claims or lien exposure, failure to pay subcontractors, reasonable evidence the work cannot be finished for the unpaid balance, or persistent failure to perform to the documents. The owner's cash flow is not a reason, and the architect has to state the reasons.
In your books: A201 Article 9 holds the schedule of values (§9.2) and the grounds for withholding certification (§9.5). Tab both.
Part 3 of 5
Substantial completion
This is the pivot date of the whole job. Know who prepares what, and what the date sets in motion.
Substantial completion is the pivot date
Substantial completion (A201 §9.8) is when the owner can occupy or use the work for its intended purpose — punch list items can remain. It starts the one-year correction period (§12.2), shifts utilities and insurance responsibility, and triggers retainage release provisions. The correction period runs from substantial completion, not final payment.
Substantial completion: who does what
The contractor moves first: when it considers the work, or a designated portion, substantially complete, it prepares its own list of items to finish or correct. The architect inspects and, if it agrees, prepares the certificate (AIA G704), which fixes the date and assigns responsibility for security, maintenance, heat, utilities, and insurance. Portions the owner occupies early can be certified separately, and each portion's correction period runs from its own date. Delay damages stop at substantial completion.
In your books: A201 §9.8 covers substantial completion, and §12.2 covers the one-year correction period.
Part 4 of 5
Final payment and closeout
Closeout is a checklist, and the last items on it protect the owner and the surety. Accepting final payment also has consequences for the contractor.
Closeout has a checklist
Punch list completion, record drawings (as-builts marked with actual installed conditions), warranties and O&M manuals, and — on bonded jobs — the surety's consent to final payment (G707). Releasing retainage without surety consent can prejudice the surety's rights and impair the owner's bond protection.
Final payment, and what it waives
Final payment, retainage included, needs releases and waivers of lien, an affidavit that debts connected with the work are paid, the surety's consent to final payment, and the closeout documents: warranties, record drawings, O&M manuals. Accepting final payment generally waives the contractor's claims that arose before it, so reserve any open claim in writing first. The one-year correction period is a duty to come back and fix nonconforming work on written notice; it is in addition to other warranty obligations and does not limit them.
Worked example
- Step 1Contractor's list of items to complete or correct
Submitted with the request for inspection
- Step 2Architect inspects and issues the certificate of substantial completion
G704 fixes the date; the correction period starts and delay damages stop
- Step 3Punch list finished; closeout documents delivered
Warranties, record drawings, O&M manuals, training
- Step 4Final payment
With lien releases, affidavit of debts paid, and consent of surety
- +1 yearCorrection period ends
Measured from substantial completion, not final payment
In your books: A201 §9.10 covers final payment. Consent of surety is AIA G707.
Part 5 of 5
Records that hold up later
When a dispute comes, the paper made at the time of the work carries the most weight. Build the habit from day one.
Records made at the time win later
Daily reports written in the ordinary course of the work (weather, crew counts by trade, equipment, areas worked, visitors, deliveries, problems) carry far more weight than anything reconstructed afterward. Meeting minutes are sent out promptly so people can object while it is fresh; minutes nobody challenged become a strong record. Record drawings are marked up as the work is done, not from memory at the end. Closeout goes better when the requirements are pulled from each spec section at the start of the job.
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Retainage
- Typically 5–10% withheld from each progress payment until completion (A201 Art. 9)
- Schedule of values
- Allocates the contract sum by work item; basis for reviewing pay applications (A201 §9.2)
- Substantial completion
- Owner can occupy/use the work for its intended purpose (A201 §9.8)
- Correction period
- 1 year from substantial completion (A201 §12.2)
- Consent of surety
- Obtain before final payment/retainage release on bonded work (AIA G707)
- Record drawings (as-builts)
- Site set marked with actual installed conditions and deviations (A201 §3.11)
- Payment due
- (Completed to date × (1 − retainage)) − previous payments
- Retainage to 50%
- Withheld on the first half only when the contract says so; none after
- Front-loading
- Overstating early schedule-of-values lines; overpays ahead of work earned
- Stored materials
- Billable on G703 with invoices, secure storage, and insurance
- Withholding certification
- Only to protect the owner for stated causes — A201 §9.5
- Submittal order
- Contractor reviews and approves first, then the architect — A201 §3.12
- RFI
- Clarifies the documents; does not change the sum or time by itself
- Contractor's list
- Contractor prepares the items to complete or correct before the architect inspects — A201 §9.8
- Certificate of substantial completion
- AIA G704, prepared by the architect; fixes the date
- Partial occupancy
- Each designated portion gets its own date and correction period
- Final payment package
- Lien releases, affidavit of debts paid, consent of surety, closeout documents — A201 §9.10
- Accepting final payment
- Waives prior claims unless reserved in writing
- Correction period vs warranty
- An added one-year remedy; it does not limit other warranties
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
- AIA Documents · 16 recommended tabsA201 article numbers are the map: Art. 3 contractor, Art. 7 changes, Art. 8 time, Art. 9 payments, Art. 11 insurance, Art. 12 corrections, Art. 14 termination, Art. 15 claims. Most Contract Admin questions cite one of these.
- Lien Law (FS 713) · 9 recommended tabsLien questions are deadline questions. Tab the deadline sections and answer from the statute, not from memory — one wrong number is the difference between a right and wrong answer.
Reading isn't learning. Retrieval is.
33 questions in this domain, each with an explanation and source.