Licenses, Permits & Inspections
20% of this examContent Area C of the outline (one question in five): which license may do which work under FS 489 and the board's rules in 61G4, what the licensing law demands of the contractor (qualifying agents, license numbers, deposits and permits, renewal, continuing education, discipline), who is exempt (owner-builders, casual minor work), what needs a permit and what does not, the inspection sequence, threshold and special inspections, the certificate of occupancy, the Notice of Commencement, Chapter 558's pre-suit defect process, and the Homeowners' Construction Recovery Fund. Nearly every answer is printed in the Contractor's Manual or the code.
What the exam asks
- Which license may do which work: general, building and residential scopes, certified versus registered, and the qualifying agent.
- What the licensing law demands of the contractor: license numbers, deposits and permit deadlines, renewal, continuing education and discipline.
- The narrow exemptions (owner-builder, casual or minor work) and what unlicensed contracting costs.
- The permit-to-occupancy path: inspection order, Notice of Commencement, threshold and special inspections, certificate of occupancy.
- Chapter 558 pre-suit defect notices and the Homeowners' Construction Recovery Fund.
Part 1 of 5
Who may do what: scopes and the qualifying agent
Every question in this area starts with the license in your hand. Know what each class may build, where a certified or registered license works, and who answers for the business.
Scopes: GC unlimited, BC three stories, RC three families and two stories
A building contractor may also remodel any size building if structural members are untouched. Division I contractors subcontract electrical, mechanical, plumbing, roofing, sheet metal, pool, and A/C work unless licensed for it, with exceptions: a GC may shingle its own new building, GCs may do site work anywhere (BC/RC on their own lot), and none must subcontract structural pool work. Certified = statewide by exam; registered = local competency, local jurisdictions only. A business contracts only through a qualifying agent; the primary agent also owns the finances.
Certified, registered, and the qualifying agent
Certification is statewide: pass the state exams and meet the experience and financial requirements. Registration rests on a local certificate of competency and is good only in the jurisdictions where the contractor holds it. A business may contract only through a licensed qualifying agent. Every qualifying agent is responsible for supervising the business's operations; the primary qualifying agent is also responsible for all financial matters. When the agent leaves, the board must be told, existing work may be finished with the board's permission, and new contracting stops until a new agent is in place.
In your books: FS 489 is reprinted in the Contractor's Manual. Tab 489.105 (definitions and scopes), .113 (subcontracting) and .119 (qualifying agents).
Part 2 of 5
What the law demands of the licensee
A license comes with duties: your number on paper, deposit deadlines, renewal on time, conduct the board can discipline, and the local registration a city or county may ask for. This is mostly recall, so learn the dates and counts exactly.
What the law demands of the licensee
License number on every contract, permit application, and ad. A deposit over 10% of the price means permits applied for within 30 days and work started within 90 days of issuance. Residential contracts over $2,500 carry the Recovery Fund notice. Renew every two years with the board's continuing education hours; a lapsed license goes delinquent, then null and void. Abandoning a job (90 days without cause), unpaid liens the owner paid for, misapplying funds, and lending a license to an unlicensed person are disciplinary grounds. Unlicensed contractors cannot enforce their contracts or lien.
Discipline and renewal
The disciplinary statute reaches financial mismanagement that harms the customer (liens the owner had to pay, abandonment, misapplied funds), building code violations, aiding unlicensed contracting, and failing to honor a repair order. Licenses renew every two years: certified licenses expire August 31 of even-numbered years, registered licenses in odd-numbered years. Renewal needs the board's continuing education hours from approved providers, including an advanced building code course and, for Division I, wind mitigation methodology.
Local and environmental approvals
A certified contractor can work anywhere in the state, but a city or county may require it to register the license with the building department, show insurance and workers' compensation, and pay the local business tax. Impact fees are local charges authorized by state statute and must be tied to the development's impact. Stormwater and wetland impacts are permitted by the water management districts and DEP under the environmental resource permit program.
Worked example
- Day 0Contractor takes more than 10% of the contract price
For work that needs a permit
- +30 daysApply for the permits
- Permit issuedThe 90-day clock starts
- +90 daysWork must have started
Unless the parties agreed otherwise in writing
In your books: In the Contractor's Manual, tab 489.126 (deposits), .129 (discipline) and .1425 (Recovery Fund notice).
Part 3 of 5
Exemptions and unlicensed work
The exemptions are narrow, and the exam tests where they end. Working without a license, or on a delinquent one, costs the contractor in ways the owner does not pay.
The exemptions are narrow
The owner-builder exemption covers an owner building or improving a one- or two-family residence, a farm outbuilding, or a commercial building within the statutory value limit, for the owner's own use. The owner signs the disclosure in person, may not hire unlicensed people for licensed work, and loses the exemption if the building is sold or leased within one year of completion. The casual-or-minor-work exemption has a dollar threshold printed in the statute and is lost if the job is part of a larger project, if the person holds himself out as a contractor, or if the work needs a trade license.
Unlicensed work has teeth on both sides
A contract made by an unlicensed contractor cannot be enforced by that contractor, and the lien law denies it lien rights; the owner can still enforce the contract against it. For licensees, aiding or abetting an unlicensed person, lending a license, or pulling a permit for work the licensee is not contracted to do are grounds for discipline. Contracting on a delinquent license is unlicensed contracting.
In your books: In the Contractor's Manual, tab 489.103 (exemptions) and .127 to .128 (unlicensed work).
Part 4 of 5
Permits, inspections and occupancy
This is the order of events on a job. Know what needs a permit, what gets inspected and when, and what has to happen before anyone may occupy the building.
Permits, inspections, and occupancy
A permit is required to construct, alter, repair, demolish, or change occupancy and for trade work; painting, flooring, cabinets, and the code's short list are exempt from the permit, not from the code. Applications abandoned and permits unstarted or idle for six months expire. Inspections follow construction (foundation/slab → frame after rough-ins → insulation → wall cover → final) and work may not be covered before approval; flood zones add a lowest-floor elevation certificate. Threshold buildings (over 3 stories or 50 feet, or assembly over 5,000 SF and 500 people) need a threshold inspector; special inspections cover welding, bolting, concrete, masonry, and soils. No occupancy without a CO or TCO. A recorded Notice of Commencement must be on file before the first inspection on jobs over the lien law threshold.
Before the first inspection: the Notice of Commencement
The lien law requires the owner to record a Notice of Commencement before improvements above the statutory dollar threshold begin. The building department may not perform the first inspection until a certified copy is filed and posted. The Notice identifies the owner, contractor, surety, and lender for everyone who will serve notices.
Threshold buildings and special inspections
A threshold building is over three stories or 50 feet, or has an assembly occupancy over 5,000 square feet with more than 500 occupants. The engineer or architect of record prepares a structural inspection plan, a licensed threshold inspector inspects the structural work and keeps a log, and no permit issues without the plan. Special inspections under the building code's Chapter 17 add expert inspection of welding, bolting, concrete, masonry, soils and piles, and sprayed fireproofing.
Occupancy, stop-work orders, and flood elevations
A new building, or a changed occupancy, may not be occupied until the building official issues a certificate of occupancy after final inspections; a temporary certificate can cover a safe portion. The official may stop work done contrary to the approved documents or the code, or done dangerously, until the violation is corrected. In flood hazard areas the lowest floor elevation is certified when the floor is in place, before the walls go up, with a final elevation certificate at the end.
Worked example
- Before workPermit issued; Notice of Commencement recorded and posted
No first inspection without the certified copy
- FoundationFooting and slab reinforcement inspected before the pour
- FrameFraming inspection after the rough electrical, plumbing, and mechanical
Nothing is covered until it is approved
- InsulationInsulation and energy items inspected before wall cover
- FinalFinal inspections, then the certificate of occupancy
No occupancy before the CO
In your books: Permits, exemptions, expiration, inspections and the certificate of occupancy are in FBC Building Chapter 1 (§105, §110, §111). Threshold buildings are FS 553.79 and special inspections are FBC Chapter 17.
Part 5 of 5
When a defect claim or a loss reaches you
Two processes sit at the end of the licensing law. Chapter 558 comes before a defect lawsuit, and the Recovery Fund pays certain residential owners who cannot collect a final order or judgment against a licensed Division I contractor.
Chapter 558 and the Recovery Fund
Before suing over a construction defect, the owner serves a written notice of claim; the contractor may inspect and must respond with an offer to repair, a monetary offer, or a dispute within the statutory period, and forwards the notice to the subs and suppliers involved. The Recovery Fund pays residential owners who hold an uncollectible final order or judgment against a licensed Division I contractor for specified violations, capped per claim and per licensee; the contractor's license is suspended until the Fund is repaid.
In your books: Read the printed days in the Chapter 558 statute rather than relying on memory. Association claims have longer periods. The Recovery Fund sections are .140 to .143 in the Contractor's Manual.
Know these cold
The short list to have in your head on exam day. Every line is also a card in your flashcards.
- Scopes
- GC unlimited; BC ≤ 3 stories (remodel any size, non-structural); RC 1–3 family, ≤ 2 habitable stories — 489.105(3)
- Deposit > 10%
- Permits applied for within 30 days; work within 90 days of issuance — 489.126
- Recovery Fund notice
- Residential contracts over $2,500 — 489.1425
- Abandonment
- 90 consecutive days without just cause — 489.129
- Permit expiration
- Not started, or idle, for six months — FBC 105.4
- Threshold building
- > 3 stories or > 50 ft, or assembly > 5,000 SF and > 500 occupants — FS 553.79
- Certified vs registered
- Statewide by state exam vs local competency in named jurisdictions — FS 489.105, 489.117
- Primary qualifying agent
- Supervision plus all financial matters — FS 489.119
- Qualifying agent leaves
- Notify the board; finish existing work by permission; no new contracts
- Owner-builder
- Own use; exemption lost if sold or leased within 1 year of completion — FS 489.103(7)
- Unlicensed contractor's contract
- Unenforceable by the contractor; no lien rights — FS 489.128
- Renewal
- Every two years; certified expire Aug 31 of even years, registered in odd years — FS 489.115
- GC shingle exception
- Shingle roofing on a new building of its own construction only — FS 489.113(3)
- Structural pool work
- Division I contractors need not subcontract it; pool electrical and plumbing still go to licensees
- Notice of Commencement
- Recorded before work; certified copy posted before the first inspection — FS 713.13
- Inspection rule
- Do not cover work until it is inspected and approved — FBC §110
- Special inspections
- Welding, bolting, concrete, masonry, soils, fireproofing — FBC Ch. 17
- Certificate of occupancy
- Required before occupancy or a change of occupancy — FBC §111
- Chapter 558 response
- Offer to repair, offer money, dispute, or a combination — FS 558.004
- Recovery Fund limits
- Residential owners, licensed Division I contractors, capped per claim and per licensee — FS 489.143
Where it lives in your books
The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.
- Licensing Law (FS 489) · 8 recommended tabsKnow the layout cold: definitions up front (489.105), business/qualifying-agent rules in the 489.119–489.1195 range, prohibitions and penalties at 489.127–489.129.
- Contractor's Manual · 8 recommended tabsThis is your home base on exam day. Learn its table of contents — most candidates lose time flipping because they never learned which chapter holds which statute.
- Florida Building Code · 18 recommended tabsCode questions give themselves away with words like 'minimum', 'required', or 'permitted'. Go to the code — never answer a code question from memory when the book is on the desk.
- Lien Law (FS 713) · 9 recommended tabsLien questions are deadline questions. Tab the deadline sections and answer from the statute, not from memory — one wrong number is the difference between a right and wrong answer.
Reading isn't learning. Retrieval is.
45 questions in this domain, each with an explanation and source.