Estimating & Bid Pricing

15% of this exam

Content Area A of the Contract Administration outline: building the number before the bid. Quantity takeoff, material/labor/equipment costing, overhead, square-foot (systems) estimating, fixed versus variable costs, break-even, markup versus margin, financing the cash-flow gap, and the regulatory costs (impact fees, permits, stormwater, OSHA) that belong in the price. Mostly arithmetic with a few definitions.

What the exam asks

  • Markup, margin and break-even arithmetic: price = cost ÷ (1 − margin), and break-even revenue = fixed costs ÷ contribution margin.
  • Unit prices built from a crew's daily production, with every worker and the labor burden counted.
  • Sorting a cost into direct cost, job overhead (general conditions) or home-office overhead.
  • Which estimate fits the drawings in hand, and how to level subcontractor quotes before comparing them.

Part 1 of 4

Pick the estimate that fits the drawings

Every estimate starts with one question: how much design exists? The answer decides whether a quick area-based number is honest or whether the job needs a full takeoff.

Square-foot estimates and what they are for

Area × historical cost per square foot gives a feasibility number fast, and a wide one. It is replaced by a detailed takeoff when drawings exist. Estimating software speeds takeoff and applies the company's assemblies, but the estimator still verifies scope, scale, and addenda.

Work it: Square-foot estimate

Budget = Area × Cost per square foot

SF
$

Feasibility budget

24,000 SF × $95 equals $2,280,000

Match the estimate to the drawings you have

With little design information, an order-of-magnitude or square-foot estimate from historical costs is the right tool, and everyone understands the accuracy is rough. Precision improves as the design develops. By the time drawings are 90% through design development there is enough to do a real quantity takeoff, and that is what a guaranteed maximum price commitment requires.

Part 2 of 4

Price the work: quantities, labor and equipment

A detailed estimate is built from the bottom up. Count the work, work out what a crew and its machines cost per day, and divide by what they produce. That gives the unit price everything else rests on.

From takeoff to unit price

Takeoff converts drawings into quantities in the unit being priced (CY, SF, LF), with waste added where the material is cut. Labor is priced from crew production at the burdened wage. Equipment carries ownership plus operating cost per hour. Subcontractor quotes are leveled for inclusions before the low one is used. General conditions (job overhead) are priced per job, and home-office overhead is recovered through markup.

Labor: production rate, crew cost, burden

Labor is priced from what a crew produces in a day. Count every worker in the crew; pricing one of two is the standard trap. Labor is priced at the burdened rate, not the bare wage: FICA, unemployment taxes, workers' compensation, payroll-based liability insurance, and fringes ride on top of the base wage.

Work it: Crew-days

Crew-days = Quantity ÷ Daily production

SF
SF

Time for the crew

12,000 SF ÷ 800 SF equals 15.0 crew-days

Work it: Unit labor cost

Unit labor cost = Daily crew cost ÷ Daily production

$
SF

Daily crew cost (every worker counted)

2 × $38 × 8 equals $608

Labor cost per SF

Daily crew cost ÷ 300 SF equals $2.03

Equipment: ownership plus operating

Ownership costs run whether or not the machine turns a wheel: depreciation, interest, taxes, insurance, storage. Operating costs occur only when it works: fuel, lubricants, filters, tires or tracks, wear parts, routine repairs. The hourly rate spreads ownership over the expected annual hours and adds the operating cost per hour. The operator is priced separately as burdened labor. Rented equipment is the rental rate plus mobilization.

Building a unit price

A unit price is material + labor + equipment for one unit of work. Multiply it by the takeoff quantity. Waste goes on the material quantity before pricing.

Work it: Unit price

Unit price = Material + Labor + Equipment, each for one unit of work

$
$
$
LF

Labor per LF

$120 ÷ 20 LF equals $6.00

Equipment per LF

$30 ÷ 20 LF equals $1.50

Unit price per LF

Material + labor + equipment equals $15.50

What one LF costs$15.50

  • Material
  • Labor
  • Equipment
Work it: Order quantity

Order quantity = Net quantity × (1 + Waste)

SF
%

Quantity to order

2,000 SF × (1 + 8%) equals 2,160 SF

In your books: Walker's is the takeoff and productivity reference, and it is a study-only book for this exam, so the conversions and crew outputs have to be in your head.

Part 3 of 4

Complete the cost: quotes, overhead and risk

Your own crews are only part of the number. Subcontractor quotes, the cost of running the job site, and the money set aside for what is not yet known all have to land in the estimate, each in the right place.

Leveling subcontractor quotes

Quotes rarely cover the same scope: one leaves out scaffolding, another the top-of-wall fire caulking. A scope sheet lists every required item against every quote so the gaps can be priced. Add the missing cost to the incomplete quote, then compare. The GC's bid has to cover the whole specified scope no matter what a sub excluded, so an unpriced hole comes straight out of the GC's pocket. The apparent low quote is often not the real low once the holes are filled.

Direct cost, job overhead, home-office overhead

Sort every cost into one of three bins. Direct costs are the labor, material, and equipment built into a specific work item (footing rebar, drywall, structural steel). Job overhead, also called general conditions, is what it takes to run this project without belonging to one item: the superintendent, field office, temporary power, dumpsters, cleanup, a night security guard. Home-office overhead (rent, office staff, principals) is not charged to a job at all; it is recovered through markup. Exam questions hand you a cost and ask which bin it goes in.

Risk and regulation in the price

Liquidated damages turn schedule risk into dollars per day; price the acceleration or a contingency, not the whole duration. The cash-flow gap (pay now, get paid in 30+ days less retainage) has a financing cost. Impact fees, permit fees, environmental permits and their controls, and OSHA compliance are project costs, not overhead.

Allowance, contingency, escalation

An allowance is a stated dollar amount for a KNOWN item whose selection is not made yet; the price adjusts up or down when the owner picks. A contingency is a reserve for the UNKNOWN: estimating variance, small scope gaps, risk nobody can assign to a line. Escalation prices work at the cost level expected when it will actually be bought, item by item. It matters for long jobs and volatile, unlocked materials like structural steel; it does not apply to a subcontract price already fixed by a signed agreement.

Part 4 of 4

Turn cost into a price

Cost is what the job takes to build. Price is what you bid. The gap between them has to carry the home office and the profit, and this is where the exam's arithmetic is concentrated.

Overhead, break-even, markup, and margin

Fixed costs continue with no work, and variable costs follow volume. Break-even is the revenue at which the contribution margin has paid for the fixed costs. Markup is figured on cost and margin on price, so the same percentage gives two different prices.

Work it: Break-even

Break-even revenue = Fixed costs ÷ Contribution margin

$
%

Revenue needed to break even

$600,000 ÷ 20% equals $3,000,000

Work it: Markup versus margin

Markup is figured on cost. Margin is figured on price.

$
%

Price at 20% markup on cost

$400,000 × (1 + 20%) equals $480,000

Price at 20% margin on price

$400,000 ÷ (1 − 20%) equals $500,000

Markup on cost$480,000

Margin on price$500,000

  • Cost
  • Profit

Markup goes on the full cost

Markup applies to direct cost plus general conditions, not to direct cost alone. Marking up only the direct cost earns nothing on the job overhead. Where overhead and profit are separate percentages, apply them in sequence instead of adding them together.

Work it: Markup on the full cost

Bid = (Direct cost + General conditions) × (1 + Markup)

$
$
%

Markup on direct cost only (the mistake)

$500,000 × (1 + 15%) + $40,000 equals $615,000

Markup on the full cost

($500,000 + $40,000) × (1 + 15%) equals $621,000

Markup on direct cost only$615,000

Markup on the full cost$621,000

  • Direct cost
  • General conditions
  • Markup
Work it: Overhead, then profit

Price = Cost × (1 + Overhead) × (1 + Profit)

$
%
%

Adding the percentages (the mistake)

$800,000 × (1 + 8% + 10%) equals $944,000

Overhead first, then profit on top

$800,000 × (1 + 8%) × (1 + 10%) equals $950,400

Percentages added$944,000

Applied in sequence$950,400

  • Cost
  • Overhead
  • Profit

In your books: The Contractor's Manual's estimating and financial chapters hold the break-even, markup and overhead definitions. The formulas themselves are not in any book on the desk.

Know these cold

The short list to have in your head on exam day. Every line is also a card in your flashcards.

Crew-days
Quantity ÷ daily crew output
Break-even
Fixed costs ÷ contribution margin (1 − variable cost ratio)
Margin to price
Price = cost ÷ (1 − margin)
Markup on cost
Cost × (1 + markup); 20% markup ≈ 16.7% margin
Square-foot estimate
Area × $/SF, order-of-magnitude only
Equipment rate
Ownership (depreciation, interest, insurance, taxes, storage) + operating (fuel, repairs)
Unit labor cost
Daily crew cost ÷ daily production (count every worker)
Unit price
Material + labor + equipment per unit of work
Order quantity
Net quantity × (1 + waste factor); 2,000 SF at 8% = 2,160 SF
Labor burden
FICA, unemployment tax, workers' comp, payroll-based liability, fringes on top of the wage
General conditions
Job overhead: superintendent, field office, temp power, dumpsters, security
Home-office overhead
Not a job cost; recovered through markup
Allowance vs contingency
Allowance = known item, undecided selection; contingency = reserve for the unknown
Escalation
Prices work at the cost level when it will be bought; not for prices already locked
Quote leveling
Add the cost of excluded scope to a quote before comparing it
Compounded markup
Cost × (1 + overhead) × (1 + profit), applied in sequence
Estimate for a GMP
Detailed takeoff from developed drawings, not a square-foot number
Operating vs ownership
Operating only when the machine works; ownership all year

Where it lives in your books

The real exam is open book. Knowing which book and which tab answer this topic is worth as much as memorizing it.